This is a clone of the Texas Administrative Code (TAC) for educational purposes. It is not the official version and should not be used for legal purposes. Site created Wed, 21 May 2025 21:16:52 GMT
Within 10 days after beginning actual construction of a project, the executive director shall be notified in writing of the date work began. Thereafter, monthly reports of progress shall be forwarded to the executive director by the 10th day of each month during construction. The report shall show the work accomplished during the month, the percentage of time used, and the percentage of completion of the project as of the close-out date of the report. In addition, the report shall show the inclusive dates of the reporting period.